Building a Quick Estimation Template When You Have Almost Nothing to Go On
# Building a Quick Estimation Template When You Have Almost Nothing to Go On When faced with vague requirements and tight deadlines, I built a simple three-pillar framework using Innovation, Scope, and People for estimating quickly.
Why You Need a Quick Estimation Template
There are moments in project management when leadership asks, “How long will this take?” and all you have is a one-liner and a deadline. Requirements are nebulous, resources are uncle..." conclusionTitle: From Fog to Forecast in Under an Hour conclusionSummary: When you’re asked for a number with almost no details, the three-pillar framework—Innovation, Scope, and People—lets you produce a fast, defensible range. Score each pillar, apply simple multipliers, and translate scope into person-days to deliver P50/P70/P90 estimates with explicit assumptions. Pair it with a 15-minute estimation interview and a one-page template, then calibrate as you learn to improve accuracy over time. conclusionKeyHeading: Speed, Clarity, and Credibility Beat Perfection conclusionKeyText: Turn uncertainty into transparent assumptions, visible trade-offs, and defensible ranges using I/S/P scores and P50/P70/P90 outputs. The result is an estimate you can explain in minutes and refine as reality unfolds. conclusionText: Grab the one-page template, run the 15-minute estimation interview on your next request, and publish a P50/P70/P90 range with assumptions today. Track actuals against your estimate, tighten the multipliers, and plug the JSON/YAML inputs into your tooling so your next estimate is even faster and sharper. seo: title: Building a Quick Estimation Template titleSuffix: description: When faced with vague requirements and tight deadlines, I built a simple three-pillar framework using Innovation, Scope, and People for estimating quickly. keywords: estimation framework, Innovation Scope People, three-pillar estimation, project estimation, calibrated multipliers, agile estimation canonical: https://markhazleton.com/articles/building-a-quick-estimation-template.html robots: index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1 og: title: Building a Quick Estimation Template With Nothing to Go On description: When faced with vague requirements, I built a simple three-pillar framework using Innovation, Scope, and People to estimate quickly and refine with data. type: article image: null imageAlt: Building a Quick Estimation Template - Mark Hazleton twitter: title: Quick Estimation Template description: "My approach to estimating with limited info: (Innovation + Scope + People) × Multiplier. Simple math, calibrated with real data." image: null imageAlt: Building a Quick Estimation Template - Mark Hazleton youtubeUrl: null youtubeTitle: null
Building a Quick Estimation Template When You Have Almost Nothing to Go On
When faced with vague requirements and tight deadlines, I built a simple three-pillar framework using Innovation, Scope, and People for estimating quickly.
Category: Project Management
Why You Need a Quick Estimation Template
There are moments in project management when leadership asks, “How long will this take?” and all you have is a one-liner and a deadline. Requirements are nebulous, resources are unclear, and the risks are unknown—yet you still need a number. In these situations, you don’t need a perfect plan; you need a credible, defensible, and quick estimate that communicates uncertainty honestly.
This article presents a pragmatic, repeatable approach built around a three-pillar model—Innovation, Scope, and People—to deliver fast estimates with traceable logic. It helps you move from “I have almost nothing” to “Here’s a 50/70/90 estimate with assumptions,” in under an hour.
Principles of Estimating in the Fog
- Fast over perfect: Provide a bounded, defensible range within 30–60 minutes.
- Honest uncertainty: Communicate confidence levels and assumptions up front.
- Repeatable structure: Use a compact template you can refine over time.
- Calibrate as you learn: Track real vs. estimated to tighten multipliers.
- Visible trade-offs: Show how adding information reduces uncertainty.
For context, see the Cone of Uncertainty, which shows how estimates become more accurate as knowledge increases: https://en.wikipedia.org/wiki/Cone_of_Uncertainty
The Three-Pillar Framework
At low fidelity, everything collapses into three drivers:
- Innovation (I): How novel is this work?
- Scope (S): How much work do we think is included?
- People (P): Who’s doing it, and how are they organized?
Each pillar is scored quickly on a 1–5 scale. Scores map to multipliers that inflate or deflate the base estimate. This keeps the math simple and the reasoning explainable.
Pillar 1: Innovation (Novelty and Uncertainty)
- 1 – Purely routine work with playbooks
- 2 – Minor variations on familiar patterns
- 3 – Some unknowns; expected trial-and-error
- 4 – High novelty; integration with unfamiliar tech
- 5 – R&D-like; unclear feasibility
What to ask:
- Is there precedent internally or externally?
- Are there new technologies, vendors, or APIs?
- Are there unknown performance/security/stability constraints?
- Will we prototype or spike to learn?
Pillar 2: Scope (Breadth and Depth)
- 1 – Single small deliverable
- 2 – A few related deliverables with limited integration
- 3 – Moderate set of deliverables with some cross-team dependencies
- 4 – Complex feature set; multi-system integrations
- 5 – Program-level scope; many moving parts
What to ask:
- What’s in vs. out of scope (even roughly)?
- How many components, integrations, or environments?
- What are the dependencies or non-functional requirements?
- What does “done” mean?
Pillar 3: People (Capability and Configuration)
- 1 – Expert team with proven track record in this domain
- 2 – Strong team, one or two gaps
- 3 – Capable team; limited domain experience; some context switching
- 4 – Mixed capabilities; changing priorities; partial availability
- 5 – New team; low availability; external coordination
What to ask:
- Who is available and for how many hours per week?
- Do we have domain expertise?
- Are roles covered (e.g., engineering, QA, design, PM)?
- Are decision-makers accessible?
The Scoring Matrix and Multipliers
Use scores to select multipliers. These are starting points; calibrate them to your org.
| Pillar | Score | Multiplier | Heuristic description |
|---|---|---|---|
| Innovation | 1 | 0.90 | Routine, low uncertainty |
| 2 | 1.00 | Familiar work | |
| 3 | 1.20 | Some unknowns | |
| 4 | 1.50 | High novelty | |
| 5 | 2.00 | R&D/prototype | |
| Scope | 1 | 0.80 | Very limited |
| 2 | 1.00 | Small-to-medium | |
| 3 | 1.30 | Moderate complexity | |
| 4 | 1.60 | Complex integrations | |
| 5 | 2.20 | Program-level | |
| People | 1 | 0.85 | Elite, stable team |
| 2 | 1.00 | Strong coverage | |
| 3 | 1.20 | Gaps or context switching | |
| 4 | 1.50 | Availability issues | |
| 5 | 1.90 | New team / external |
Notes:
- Innovation and Scope usually inflate the estimate as they rise.
- People often inflates when less optimal (higher score = larger multiplier).
- Multipliers compound: TotalMultiplier = I × S × P.
A Minimal Estimation Formula
- Start with a base scope size in abstract units (e.g., story points or T-shirt sizes converted).
- Translate into person-days using a baseline throughput.
- Apply multipliers to account for innovation, scope uncertainty, and team factors.
- Add a contingency consistent with confidence levels.
Suggested defaults:
- Baseline throughput: 1 story point ≈ 0.75 person-days (adjust per team)
- Alternatively: 1 small feature ≈ 3–5 days; 1 integration ≈ 5–10 days
Formula:
- Base person-days = ScopeUnits × Throughput
- Adjusted person-days = Base × I × S × P
- 50% estimate (P50) = Adjusted
- 70% estimate (P70) = P50 × 1.2
- 90% estimate (P90) = P50 × 1.5
These P50/P70/P90 factors are simple proxies when you can’t run full risk modeling. Replace with your own calibrated ratios over time.
Quick Start: 15-Minute Estimation Interview
Ask:
- What is the primary outcome? What does “done” look like?
- What’s in/out? Name three things definitely not included.
- Who is available? Any hard capacity limits?
- Which systems are involved? Any new vendors or tech?
- What date is driving this? What is flexible?
Then:
- Assign I/S/P scores.
- Choose a rough scope unit count (e.g., 8–15 points).
- Compute P50/P70/P90.
The One-Page Estimation Template (Markdown)
Copy/paste this into your ticket, doc, or email.
# Quick Estimate — <Project/Feature Name>
Date: <YYYY-MM-DD>
Estimator: <Name>
Confidence: P50/P70/P90
Outcome (one-liner):
- <Describe the measurable outcome or deliverable>
Assumptions:
- <List key assumptions>
- <What’s explicitly out-of-scope>
Three-Pillar Scores:
- Innovation (I): <1–5> → Multiplier: <X.XX>
- Scope (S): <1–5> → Multiplier: <X.XX>
- People (P): <1–5> → Multiplier: <X.XX>
Scope Size:
- Units: <story points / features / tasks>
- Quantity: <N>
- Throughput: <units-to-days conversion>
Math:
- Base person-days = <N × throughput>
- Adjusted = Base × I × S × P
- P50 = <Adjusted>
- P70 = <Adjusted × 1.2>
- P90 = <Adjusted × 1.5>
Risks & Unknowns:
- <Top 3–5 risks>
- <Mitigations or spikes>
Dependencies:
- <Teams, vendors, approvals>
Decision/Trade-offs:
- If we drop X, we save ~Y days
- If we defer Z, risk reduces by ~R%
Next Steps (to refine estimate):
- <Spike A> (1–2 days) to validate <unknown>
- <Stakeholder review> to confirm scopeJSON/YAML Template for Tooling
If you use scripts or dashboards, you can capture inputs like this:
{
"project": "New Analytics Dashboard",
"date": "2025-01-15",
"scope_units": 14,
"throughput_days_per_unit": 0.8,
"innovation_score": 3,
"scope_score": 4,
"people_score": 2,
"multipliers": {
"innovation": { "1": 0.9, "2": 1.0, "3": 1.2, "4": 1.5, "5": 2.0 },
"scope": { "1": 0.8, "2": 1.0, "3": 1.3, "4": 1.6, "5": 2.2 },
"people": { "1": 0.85, "2": 1.0, "3": 1.2, "4": 1.5, "5": 1.9 }
},
"confidence_factors": { "p70": 1.2, "p90": 1.5 },
"assumptions": [
"Single data warehouse source",
"Two chart types at launch",
"No SSO integration in v1"
]
}project: New Analytics Dashboard
date: 2025-01-15
scope_units: 14
throughput_days_per_unit: 0.8
innovation_score: 3
scope_score: 4
people_score: 2
confidence_factors:
p70: 1.2
p90: 1.5
assumptions:
- Single data warehouse source
- Two chart types at launch
- No SSO integration in v1Example Walkthrough
Scenario:
- Outcome: MVP of a customer-facing dashboard with filtering and export.
- Constraints: Demo in 6 weeks.
- Team: One senior engineer (70%), one mid-level (50%), shared designer (25%).
- Risks: Unknown export format standard; new BI library.
Scores:
- Innovation (I) = 3 (some unknowns with BI library)
- Scope (S) = 4 (integrations with auth, data, export)
- People (P) = 3 (partial availability, mixed levels)
Scope and throughput:
- 16 story points at 0.75 days/point
- Base = 16 × 0.75 = 12 person-days
Multipliers:
- I=1.2, S=1.6, P=1.2 → Total = 1.2 × 1.6 × 1.2 = 2.304
Adjusted:
- P50 = 12 × 2.304 = 27.648 ≈ 28 person-days
- P70 = 28 × 1.2 = 33.6 ≈ 34 person-days
- P90 = 28 × 1.5 = 42 person-days
Calendar implications:
- With ~1.45 FTE (0.7 + 0.5 + 0.25×0.5 for design), say 7 person-days/week
- P50 timeline ≈ 4 weeks, P70 ≈ 5 weeks, P90 ≈ 6 weeks
- Conclusion: Demo feasible, but reserve scope cuts if risks materialize.
Trade-offs:
- Drop export v1 → save ~4–6 days; reduce risk
- Replace BI library with plain charts → save ~2–3 days learning curve
Monte Carlo Option (When You Have 10 More Minutes)
Use a simple simulation to convert multipliers and scope variance into confidence ranges.
import json, random, statistics as stats
config = {
"scope_units": 16,
"throughput_days_per_unit": 0.75,
"multipliers": {"I": 1.2, "S": 1.6, "P": 1.2},
"scope_variation": 0.25, # ±25%
"mult_variation": 0.10, # ±10% each multiplier
"trials": 5000
}
def sample_uniform(center, spread):
return random.uniform(center*(1-spread), center*(1+spread))
def simulate(cfg):
base = cfg["scope_units"] * cfg["throughput_days_per_unit"]
samples = []
for _ in range(cfg["trials"]):
scope = sample_uniform(cfg["scope_units"], cfg["scope_variation"])
i = sample_uniform(cfg["multipliers"]["I"], cfg["mult_variation"])
s = sample_uniform(cfg["multipliers"]["S"], cfg["mult_variation"])
p = sample_uniform(cfg["multipliers"]["P"], cfg["mult_variation"])
samples.append((scope * cfg["throughput_days_per_unit"]) * i * s * p)
samples.sort()
def percentile(pct): return samples[int(len(samples)*pct)]
return {
"p50": percentile(0.50),
"p70": percentile(0.70),
"p90": percentile(0.90),
"mean": stats.mean(samples),
"stddev": stats.pstdev(samples)
}
print(simulate(config))This is not over-engineering; it provides a quick sanity check on your P70/P90.
Spreadsheet-Friendly Formulas
- Base person-days:
- = ScopeUnits × Throughput
- Total multiplier:
- = I_Mult × S_Mult × P_Mult
- P50:
- = Base × TotalMult
- P70:
- = P50 × 1.2
- P90:
- = P50 × 1.5
For Google Sheets with dropdowns and a lookup table:
- Suppose A2=InnovationScore, B2=ScopeScore, C2=PeopleScore, and you have a lookup table in H2:J6 for multipliers. Then:
- I_Mult: =INDEX($H$2:$H$6, A2)
- S_Mult: =INDEX($I$2:$I$6, B2)
- P_Mult: =INDEX($J$2:$J$6, C2)
- Total: =PRODUCT(I_Mult, S_Mult, P_Mult)
Risk and Contingency: Aligning with Confidence
When nothing is certain, ranges are more honest than single numbers. Map risk appetite to buffers:
| Confidence | Factor | Use when… |
|---|---|---|
| P50 | 1.0× | Internal planning, low penalty for slippage |
| P70 | 1.2× | Stakeholder commitments with moderate risk |
| P90 | 1.5× | External commitments, penalties, or launches |
Tip:
- Quote “P70: 5 weeks (range 4–6)” rather than “5 weeks.”
- Pair with key assumptions; commit to updating within 3–5 business days as unknowns clarify.
Communication Template (Email/Slack)
Here’s a quick estimate for <Project> based on limited info:
P50: ~28 person-days
P70: ~34 person-days
P90: ~42 person-days
Assumptions:
- Single data source; no SSO
- Two visualizations at launch
- Partial team availability
Drivers (multipliers):
- Innovation=1.2 (new BI lib)
- Scope=1.6 (multiple integrations)
- People=1.2 (partial availability)
Top risks:
- Export format ambiguity
- Data quality variance
Next steps to reduce uncertainty (within 3 days):
- 1-day spike to validate export format
- Stakeholder review to confirm must-have charts
If we drop export in v1: save ~4–6 days.Calibrating Over Time
Your first multipliers are guesses. Make them better:
- Track: planned (P50) vs. actuals at a task/feature level.
- Categorize: routine vs. novel, integration-heavy vs. UI-heavy.
- Regress: adjust multipliers and throughput quarterly.
- Watch variance: if your P90 misses often, increase buffers.
- Codify: publish a 1-pager of “current org multipliers.”
Calibration practice:
- Compute Actual/Base for completed items.
- Compare by pillar scoring to see bias (e.g., people=4 often underestimates by 30%).
- Update multiplier table accordingly.
Context Variations
- Software Delivery
- Throughput via historical velocity: 1 point ≈ team-days/velocity.
- Innovation spike tickets to de-risk libraries, API quotas, infra.
- Data Projects
- Treat data quality/availability as innovation risk.
- Scope includes pipelines, transformations, lineage, validation.
- Design/Research
- Throughput in artifacts/week; innovation includes new user segments.
- Operations/Infrastructure
- People multiplier more sensitive to change windows and approvals.
- Scope includes environments, runbooks, rollback plans.
Common Pitfalls and How to Avoid Them
- Pitfall: Anchoring on a single number.
- Fix: Always present P50/P70/P90 with assumptions.
- Pitfall: Ignoring availability and context switching.
- Fix: Use People multiplier and explicit FTE assumptions.
- Pitfall: Hidden scope in non-functional requirements.
- Fix: Include deployment, security, observability in scope checklist.
- Pitfall: “Unknown unknowns” hand-waving.
- Fix: Include a time-boxed spike to turn unknowns into knowns.
- Pitfall: No follow-up refinement.
- Fix: Set a refinement checkpoint date in the estimate.
A Lightweight Risk Checklist
- Integrations: new vendor, auth, rate limits?
- Data: quality, volume, latency, privacy?
- Compliance: approvals, audit, change windows?
- Performance: SLAs, load profiles?
- Environments: dev/test/stage/prod parity, infra readiness?
- People: key person risk, onboarding time?
- External: dependencies on other teams’ backlogs?
Quick Reference: T-shirt Sizing Conversion
Use when tasks are non-technical or mixed-discipline.
| Size | Person-days (baseline) |
|---|---|
| XS | 0.5–1 |
| S | 1–3 |
| M | 3–5 |
| L | 5–8 |
| XL | 8–13 |
Then apply I/S/P multipliers just as you would for points.
Putting It All Together: A Worked Micro-Example
- Feature: “Add email passwordless login.”
- Assumptions: Use existing auth provider; mobile and web; no SSO v1.
- Scores: I=2, S=3, P=2 → Multipliers: 1.0 × 1.3 × 1.0 = 1.3
- Scope: 10 points; throughput 0.8 days/point → Base = 8 days
- P50: 8 × 1.3 = 10.4 ≈ 10.5 days
- P70: 12.6 days; P90: 15.8 days
- Communication: “P70: ~2.5 weeks for a 1-FTE engineer; risk reduced if we reuse existing session flows.”
Implementation Snippet: CLI Estimator
For quick terminal usage:
#!/usr/bin/env python3
import argparse
I_MULT = {1:0.9, 2:1.0, 3:1.2, 4:1.5, 5:2.0}
S_MULT = {1:0.8, 2:1.0, 3:1.3, 4:1.6, 5:2.2}
P_MULT = {1:0.85,2:1.0, 3:1.2, 4:1.5, 5:1.9}
def estimate(units, days_per_unit, i, s, p, p70=1.2, p90=1.5):
base = units * days_per_unit
total_mult = I_MULT[i] * S_MULT[s] * P_MULT[p]
p50 = base * total_mult
return p50, p50*p70, p50*p90
if __name__ == "__main__":
ap = argparse.ArgumentParser()
ap.add_argument("--units", type=float, required=True)
ap.add_argument("--days_per_unit", type=float, default=0.75)
ap.add_argument("--i", type=int, required=True)
ap.add_argument("--s", type=int, required=True)
ap.add_argument("--p", type=int, required=True)
args = ap.parse_args()
p50, p70, p90 = estimate(args.units, args.days_per_unit, args.i, args.s, args.p)
print(f"P50: {p50:.1f} days | P70: {p70:.1f} | P90: {p90:.1f}")Usage:
- ./estimate.py --units 16 --days_per_unit 0.75 --i 3 --s 4 --p 2
How to Present to Stakeholders
- Lead with outcomes and ranges:
- “To deliver X, we estimate P70: 5 weeks (range 4–6), assuming Y.”
- Highlight top 2–3 uncertainties and the plan to reduce them.
- Offer scope levers: “If we drop A, we save B days.”
- Time-box learning: “We’ll run a 2-day spike and report back by Friday.”
- Ask for decisions: “We need sign-off on C to hold P70.”
FAQ
- Why not just use story points?
- Points are helpful, but in early stages you still need a conversion and a way to express uncertainty. The three-pillar multipliers make your assumptions explicit.
- Isn’t multiplying multipliers risky?
- Yes, compounding can inflate quickly. That’s intentional—uncertainties multiply in real life. Calibrate to your context.
- What about fixed-price contracts?
- Use P90 or higher and enumerate assumptions in the SOW. Price change orders for scope additions or assumption violations.
- Can this work outside software?
- Yes. Substitute scope units with appropriate measures (deliverables, interviews, pages designed, servers configured).
Further Reading
- Cone of Uncertainty: https://en.wikipedia.org/wiki/Cone_of_Uncertainty
- Brooks’s Law (team scaling risks): https://en.wikipedia.org/wiki/Brooks%27s_law
- Relative estimation and Story Points: https://www.scrum.org/resources/blog/what-are-story-points
- Monte Carlo in project management: https://en.wikipedia.org/wiki/Monte_Carlo_method
Final Thoughts
When you have almost nothing to go on, the goal isn’t precision—it’s clarity. A quick, transparent estimate with Innovation, Scope, and People puts structure around ambiguity, communicates risk honestly, and creates a path to reduce uncertainty. Use this template to get to a credible P50/P70/P90 in under an hour, then iterate as you learn.
Ship the estimate, time-box the unknowns, and refine. That’s how you deliver under uncertainty.