Building a Quick Estimation Template When You Have Almost Nothing to Go On

December 28, 20255 min read

# Building a Quick Estimation Template When You Have Almost Nothing to Go On When faced with vague requirements and tight deadlines, I built a simple three-pillar framework using Innovation, Scope, and People for estimating quickly.

Why You Need a Quick Estimation Template

There are moments in project management when leadership asks, “How long will this take?” and all you have is a one-liner and a deadline. Requirements are nebulous, resources are uncle..." conclusionTitle: From Fog to Forecast in Under an Hour conclusionSummary: When you’re asked for a number with almost no details, the three-pillar framework—Innovation, Scope, and People—lets you produce a fast, defensible range. Score each pillar, apply simple multipliers, and translate scope into person-days to deliver P50/P70/P90 estimates with explicit assumptions. Pair it with a 15-minute estimation interview and a one-page template, then calibrate as you learn to improve accuracy over time. conclusionKeyHeading: Speed, Clarity, and Credibility Beat Perfection conclusionKeyText: Turn uncertainty into transparent assumptions, visible trade-offs, and defensible ranges using I/S/P scores and P50/P70/P90 outputs. The result is an estimate you can explain in minutes and refine as reality unfolds. conclusionText: Grab the one-page template, run the 15-minute estimation interview on your next request, and publish a P50/P70/P90 range with assumptions today. Track actuals against your estimate, tighten the multipliers, and plug the JSON/YAML inputs into your tooling so your next estimate is even faster and sharper. seo: title: Building a Quick Estimation Template titleSuffix: description: When faced with vague requirements and tight deadlines, I built a simple three-pillar framework using Innovation, Scope, and People for estimating quickly. keywords: estimation framework, Innovation Scope People, three-pillar estimation, project estimation, calibrated multipliers, agile estimation canonical: https://markhazleton.com/articles/building-a-quick-estimation-template.html robots: index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1 og: title: Building a Quick Estimation Template With Nothing to Go On description: When faced with vague requirements, I built a simple three-pillar framework using Innovation, Scope, and People to estimate quickly and refine with data. type: article image: null imageAlt: Building a Quick Estimation Template - Mark Hazleton twitter: title: Quick Estimation Template description: "My approach to estimating with limited info: (Innovation + Scope + People) × Multiplier. Simple math, calibrated with real data." image: null imageAlt: Building a Quick Estimation Template - Mark Hazleton youtubeUrl: null youtubeTitle: null

Building a Quick Estimation Template When You Have Almost Nothing to Go On

When faced with vague requirements and tight deadlines, I built a simple three-pillar framework using Innovation, Scope, and People for estimating quickly.

Category: Project Management


Why You Need a Quick Estimation Template

There are moments in project management when leadership asks, “How long will this take?” and all you have is a one-liner and a deadline. Requirements are nebulous, resources are unclear, and the risks are unknown—yet you still need a number. In these situations, you don’t need a perfect plan; you need a credible, defensible, and quick estimate that communicates uncertainty honestly.

This article presents a pragmatic, repeatable approach built around a three-pillar model—Innovation, Scope, and People—to deliver fast estimates with traceable logic. It helps you move from “I have almost nothing” to “Here’s a 50/70/90 estimate with assumptions,” in under an hour.


Principles of Estimating in the Fog

  • Fast over perfect: Provide a bounded, defensible range within 30–60 minutes.
  • Honest uncertainty: Communicate confidence levels and assumptions up front.
  • Repeatable structure: Use a compact template you can refine over time.
  • Calibrate as you learn: Track real vs. estimated to tighten multipliers.
  • Visible trade-offs: Show how adding information reduces uncertainty.

For context, see the Cone of Uncertainty, which shows how estimates become more accurate as knowledge increases: https://en.wikipedia.org/wiki/Cone_of_Uncertainty


The Three-Pillar Framework

At low fidelity, everything collapses into three drivers:

  1. Innovation (I): How novel is this work?
  2. Scope (S): How much work do we think is included?
  3. People (P): Who’s doing it, and how are they organized?

Each pillar is scored quickly on a 1–5 scale. Scores map to multipliers that inflate or deflate the base estimate. This keeps the math simple and the reasoning explainable.

Pillar 1: Innovation (Novelty and Uncertainty)

  • 1 – Purely routine work with playbooks
  • 2 – Minor variations on familiar patterns
  • 3 – Some unknowns; expected trial-and-error
  • 4 – High novelty; integration with unfamiliar tech
  • 5 – R&D-like; unclear feasibility

What to ask:

  • Is there precedent internally or externally?
  • Are there new technologies, vendors, or APIs?
  • Are there unknown performance/security/stability constraints?
  • Will we prototype or spike to learn?

Pillar 2: Scope (Breadth and Depth)

  • 1 – Single small deliverable
  • 2 – A few related deliverables with limited integration
  • 3 – Moderate set of deliverables with some cross-team dependencies
  • 4 – Complex feature set; multi-system integrations
  • 5 – Program-level scope; many moving parts

What to ask:

  • What’s in vs. out of scope (even roughly)?
  • How many components, integrations, or environments?
  • What are the dependencies or non-functional requirements?
  • What does “done” mean?

Pillar 3: People (Capability and Configuration)

  • 1 – Expert team with proven track record in this domain
  • 2 – Strong team, one or two gaps
  • 3 – Capable team; limited domain experience; some context switching
  • 4 – Mixed capabilities; changing priorities; partial availability
  • 5 – New team; low availability; external coordination

What to ask:

  • Who is available and for how many hours per week?
  • Do we have domain expertise?
  • Are roles covered (e.g., engineering, QA, design, PM)?
  • Are decision-makers accessible?

The Scoring Matrix and Multipliers

Use scores to select multipliers. These are starting points; calibrate them to your org.

PillarScoreMultiplierHeuristic description
Innovation10.90Routine, low uncertainty
21.00Familiar work
31.20Some unknowns
41.50High novelty
52.00R&D/prototype
Scope10.80Very limited
21.00Small-to-medium
31.30Moderate complexity
41.60Complex integrations
52.20Program-level
People10.85Elite, stable team
21.00Strong coverage
31.20Gaps or context switching
41.50Availability issues
51.90New team / external

Notes:

  • Innovation and Scope usually inflate the estimate as they rise.
  • People often inflates when less optimal (higher score = larger multiplier).
  • Multipliers compound: TotalMultiplier = I × S × P.

A Minimal Estimation Formula

  • Start with a base scope size in abstract units (e.g., story points or T-shirt sizes converted).
  • Translate into person-days using a baseline throughput.
  • Apply multipliers to account for innovation, scope uncertainty, and team factors.
  • Add a contingency consistent with confidence levels.

Suggested defaults:

  • Baseline throughput: 1 story point ≈ 0.75 person-days (adjust per team)
  • Alternatively: 1 small feature ≈ 3–5 days; 1 integration ≈ 5–10 days

Formula:

  • Base person-days = ScopeUnits × Throughput
  • Adjusted person-days = Base × I × S × P
  • 50% estimate (P50) = Adjusted
  • 70% estimate (P70) = P50 × 1.2
  • 90% estimate (P90) = P50 × 1.5

These P50/P70/P90 factors are simple proxies when you can’t run full risk modeling. Replace with your own calibrated ratios over time.


Quick Start: 15-Minute Estimation Interview

Ask:

  • What is the primary outcome? What does “done” look like?
  • What’s in/out? Name three things definitely not included.
  • Who is available? Any hard capacity limits?
  • Which systems are involved? Any new vendors or tech?
  • What date is driving this? What is flexible?

Then:

  • Assign I/S/P scores.
  • Choose a rough scope unit count (e.g., 8–15 points).
  • Compute P50/P70/P90.

The One-Page Estimation Template (Markdown)

Copy/paste this into your ticket, doc, or email.

# Quick Estimate — <Project/Feature Name>
Date: <YYYY-MM-DD>
Estimator: <Name>
Confidence: P50/P70/P90

Outcome (one-liner):
- <Describe the measurable outcome or deliverable>

Assumptions:
- <List key assumptions>
- <What’s explicitly out-of-scope>

Three-Pillar Scores:
- Innovation (I): <1–5>  → Multiplier: <X.XX>
- Scope (S): <1–5>       → Multiplier: <X.XX>
- People (P): <1–5>      → Multiplier: <X.XX>

Scope Size:
- Units: <story points / features / tasks>
- Quantity: <N>
- Throughput: <units-to-days conversion>

Math:
- Base person-days = <N × throughput>
- Adjusted = Base × I × S × P
- P50 = <Adjusted>
- P70 = <Adjusted × 1.2>
- P90 = <Adjusted × 1.5>

Risks & Unknowns:
- <Top 3–5 risks>
- <Mitigations or spikes>

Dependencies:
- <Teams, vendors, approvals>

Decision/Trade-offs:
- If we drop X, we save ~Y days
- If we defer Z, risk reduces by ~R%

Next Steps (to refine estimate):
- <Spike A> (1–2 days) to validate <unknown>
- <Stakeholder review> to confirm scope

JSON/YAML Template for Tooling

If you use scripts or dashboards, you can capture inputs like this:

{
  "project": "New Analytics Dashboard",
  "date": "2025-01-15",
  "scope_units": 14,
  "throughput_days_per_unit": 0.8,
  "innovation_score": 3,
  "scope_score": 4,
  "people_score": 2,
  "multipliers": {
    "innovation": { "1": 0.9, "2": 1.0, "3": 1.2, "4": 1.5, "5": 2.0 },
    "scope":      { "1": 0.8, "2": 1.0, "3": 1.3, "4": 1.6, "5": 2.2 },
    "people":     { "1": 0.85, "2": 1.0, "3": 1.2, "4": 1.5, "5": 1.9 }
  },
  "confidence_factors": { "p70": 1.2, "p90": 1.5 },
  "assumptions": [
    "Single data warehouse source",
    "Two chart types at launch",
    "No SSO integration in v1"
  ]
}
project: New Analytics Dashboard
date: 2025-01-15
scope_units: 14
throughput_days_per_unit: 0.8
innovation_score: 3
scope_score: 4
people_score: 2
confidence_factors:
  p70: 1.2
  p90: 1.5
assumptions:
  - Single data warehouse source
  - Two chart types at launch
  - No SSO integration in v1

Example Walkthrough

Scenario:

  • Outcome: MVP of a customer-facing dashboard with filtering and export.
  • Constraints: Demo in 6 weeks.
  • Team: One senior engineer (70%), one mid-level (50%), shared designer (25%).
  • Risks: Unknown export format standard; new BI library.

Scores:

  • Innovation (I) = 3 (some unknowns with BI library)
  • Scope (S) = 4 (integrations with auth, data, export)
  • People (P) = 3 (partial availability, mixed levels)

Scope and throughput:

  • 16 story points at 0.75 days/point
  • Base = 16 × 0.75 = 12 person-days

Multipliers:

  • I=1.2, S=1.6, P=1.2 → Total = 1.2 × 1.6 × 1.2 = 2.304

Adjusted:

  • P50 = 12 × 2.304 = 27.648 ≈ 28 person-days
  • P70 = 28 × 1.2 = 33.6 ≈ 34 person-days
  • P90 = 28 × 1.5 = 42 person-days

Calendar implications:

  • With ~1.45 FTE (0.7 + 0.5 + 0.25×0.5 for design), say 7 person-days/week
  • P50 timeline ≈ 4 weeks, P70 ≈ 5 weeks, P90 ≈ 6 weeks
  • Conclusion: Demo feasible, but reserve scope cuts if risks materialize.

Trade-offs:

  • Drop export v1 → save ~4–6 days; reduce risk
  • Replace BI library with plain charts → save ~2–3 days learning curve

Monte Carlo Option (When You Have 10 More Minutes)

Use a simple simulation to convert multipliers and scope variance into confidence ranges.

import json, random, statistics as stats

config = {
    "scope_units": 16,
    "throughput_days_per_unit": 0.75,
    "multipliers": {"I": 1.2, "S": 1.6, "P": 1.2},
    "scope_variation": 0.25,   # ±25%
    "mult_variation": 0.10,    # ±10% each multiplier
    "trials": 5000
}

def sample_uniform(center, spread):
    return random.uniform(center*(1-spread), center*(1+spread))

def simulate(cfg):
    base = cfg["scope_units"] * cfg["throughput_days_per_unit"]
    samples = []
    for _ in range(cfg["trials"]):
        scope = sample_uniform(cfg["scope_units"], cfg["scope_variation"])
        i = sample_uniform(cfg["multipliers"]["I"], cfg["mult_variation"])
        s = sample_uniform(cfg["multipliers"]["S"], cfg["mult_variation"])
        p = sample_uniform(cfg["multipliers"]["P"], cfg["mult_variation"])
        samples.append((scope * cfg["throughput_days_per_unit"]) * i * s * p)
    samples.sort()
    def percentile(pct): return samples[int(len(samples)*pct)]
    return {
        "p50": percentile(0.50),
        "p70": percentile(0.70),
        "p90": percentile(0.90),
        "mean": stats.mean(samples),
        "stddev": stats.pstdev(samples)
    }

print(simulate(config))

This is not over-engineering; it provides a quick sanity check on your P70/P90.


Spreadsheet-Friendly Formulas

  • Base person-days:
    • = ScopeUnits × Throughput
  • Total multiplier:
    • = I_Mult × S_Mult × P_Mult
  • P50:
    • = Base × TotalMult
  • P70:
    • = P50 × 1.2
  • P90:
    • = P50 × 1.5

For Google Sheets with dropdowns and a lookup table:

  • Suppose A2=InnovationScore, B2=ScopeScore, C2=PeopleScore, and you have a lookup table in H2:J6 for multipliers. Then:
    • I_Mult: =INDEX($H$2:$H$6, A2)
    • S_Mult: =INDEX($I$2:$I$6, B2)
    • P_Mult: =INDEX($J$2:$J$6, C2)
    • Total: =PRODUCT(I_Mult, S_Mult, P_Mult)

Risk and Contingency: Aligning with Confidence

When nothing is certain, ranges are more honest than single numbers. Map risk appetite to buffers:

ConfidenceFactorUse when…
P501.0×Internal planning, low penalty for slippage
P701.2×Stakeholder commitments with moderate risk
P901.5×External commitments, penalties, or launches

Tip:

  • Quote “P70: 5 weeks (range 4–6)” rather than “5 weeks.”
  • Pair with key assumptions; commit to updating within 3–5 business days as unknowns clarify.

Communication Template (Email/Slack)

Here’s a quick estimate for <Project> based on limited info:

P50: ~28 person-days
P70: ~34 person-days
P90: ~42 person-days

Assumptions:
- Single data source; no SSO
- Two visualizations at launch
- Partial team availability

Drivers (multipliers):
- Innovation=1.2 (new BI lib)
- Scope=1.6 (multiple integrations)
- People=1.2 (partial availability)

Top risks:
- Export format ambiguity
- Data quality variance

Next steps to reduce uncertainty (within 3 days):
- 1-day spike to validate export format
- Stakeholder review to confirm must-have charts

If we drop export in v1: save ~4–6 days.

Calibrating Over Time

Your first multipliers are guesses. Make them better:

  • Track: planned (P50) vs. actuals at a task/feature level.
  • Categorize: routine vs. novel, integration-heavy vs. UI-heavy.
  • Regress: adjust multipliers and throughput quarterly.
  • Watch variance: if your P90 misses often, increase buffers.
  • Codify: publish a 1-pager of “current org multipliers.”

Calibration practice:

  • Compute Actual/Base for completed items.
  • Compare by pillar scoring to see bias (e.g., people=4 often underestimates by 30%).
  • Update multiplier table accordingly.

Context Variations

  • Software Delivery
    • Throughput via historical velocity: 1 point ≈ team-days/velocity.
    • Innovation spike tickets to de-risk libraries, API quotas, infra.
  • Data Projects
    • Treat data quality/availability as innovation risk.
    • Scope includes pipelines, transformations, lineage, validation.
  • Design/Research
    • Throughput in artifacts/week; innovation includes new user segments.
  • Operations/Infrastructure
    • People multiplier more sensitive to change windows and approvals.
    • Scope includes environments, runbooks, rollback plans.

Common Pitfalls and How to Avoid Them

  • Pitfall: Anchoring on a single number.
    • Fix: Always present P50/P70/P90 with assumptions.
  • Pitfall: Ignoring availability and context switching.
    • Fix: Use People multiplier and explicit FTE assumptions.
  • Pitfall: Hidden scope in non-functional requirements.
    • Fix: Include deployment, security, observability in scope checklist.
  • Pitfall: “Unknown unknowns” hand-waving.
    • Fix: Include a time-boxed spike to turn unknowns into knowns.
  • Pitfall: No follow-up refinement.
    • Fix: Set a refinement checkpoint date in the estimate.

A Lightweight Risk Checklist

  • Integrations: new vendor, auth, rate limits?
  • Data: quality, volume, latency, privacy?
  • Compliance: approvals, audit, change windows?
  • Performance: SLAs, load profiles?
  • Environments: dev/test/stage/prod parity, infra readiness?
  • People: key person risk, onboarding time?
  • External: dependencies on other teams’ backlogs?

Quick Reference: T-shirt Sizing Conversion

Use when tasks are non-technical or mixed-discipline.

SizePerson-days (baseline)
XS0.5–1
S1–3
M3–5
L5–8
XL8–13

Then apply I/S/P multipliers just as you would for points.


Putting It All Together: A Worked Micro-Example

  • Feature: “Add email passwordless login.”
  • Assumptions: Use existing auth provider; mobile and web; no SSO v1.
  • Scores: I=2, S=3, P=2 → Multipliers: 1.0 × 1.3 × 1.0 = 1.3
  • Scope: 10 points; throughput 0.8 days/point → Base = 8 days
  • P50: 8 × 1.3 = 10.4 ≈ 10.5 days
  • P70: 12.6 days; P90: 15.8 days
  • Communication: “P70: ~2.5 weeks for a 1-FTE engineer; risk reduced if we reuse existing session flows.”

Implementation Snippet: CLI Estimator

For quick terminal usage:

#!/usr/bin/env python3
import argparse

I_MULT = {1:0.9, 2:1.0, 3:1.2, 4:1.5, 5:2.0}
S_MULT = {1:0.8, 2:1.0, 3:1.3, 4:1.6, 5:2.2}
P_MULT = {1:0.85,2:1.0, 3:1.2, 4:1.5, 5:1.9}

def estimate(units, days_per_unit, i, s, p, p70=1.2, p90=1.5):
    base = units * days_per_unit
    total_mult = I_MULT[i] * S_MULT[s] * P_MULT[p]
    p50 = base * total_mult
    return p50, p50*p70, p50*p90

if __name__ == "__main__":
    ap = argparse.ArgumentParser()
    ap.add_argument("--units", type=float, required=True)
    ap.add_argument("--days_per_unit", type=float, default=0.75)
    ap.add_argument("--i", type=int, required=True)
    ap.add_argument("--s", type=int, required=True)
    ap.add_argument("--p", type=int, required=True)
    args = ap.parse_args()
    p50, p70, p90 = estimate(args.units, args.days_per_unit, args.i, args.s, args.p)
    print(f"P50: {p50:.1f} days | P70: {p70:.1f} | P90: {p90:.1f}")

Usage:

  • ./estimate.py --units 16 --days_per_unit 0.75 --i 3 --s 4 --p 2

How to Present to Stakeholders

  • Lead with outcomes and ranges:
    • “To deliver X, we estimate P70: 5 weeks (range 4–6), assuming Y.”
  • Highlight top 2–3 uncertainties and the plan to reduce them.
  • Offer scope levers: “If we drop A, we save B days.”
  • Time-box learning: “We’ll run a 2-day spike and report back by Friday.”
  • Ask for decisions: “We need sign-off on C to hold P70.”

FAQ

  • Why not just use story points?
    • Points are helpful, but in early stages you still need a conversion and a way to express uncertainty. The three-pillar multipliers make your assumptions explicit.
  • Isn’t multiplying multipliers risky?
    • Yes, compounding can inflate quickly. That’s intentional—uncertainties multiply in real life. Calibrate to your context.
  • What about fixed-price contracts?
    • Use P90 or higher and enumerate assumptions in the SOW. Price change orders for scope additions or assumption violations.
  • Can this work outside software?
    • Yes. Substitute scope units with appropriate measures (deliverables, interviews, pages designed, servers configured).

Further Reading


Final Thoughts

When you have almost nothing to go on, the goal isn’t precision—it’s clarity. A quick, transparent estimate with Innovation, Scope, and People puts structure around ambiguity, communicates risk honestly, and creates a path to reduce uncertainty. Use this template to get to a credible P50/P70/P90 in under an hour, then iterate as you learn.

Ship the estimate, time-box the unknowns, and refine. That’s how you deliver under uncertainty.